10 December 2007
Prolojik wins Kennedy fitout at 1 Fenchurch Avenue
Prolojik has secured the lighting controls package at 1 Fenchurch Avenue for the 5 storey fitout of the Fenchurch Avenue Building. The project builds on the shell-and-core phase completed in 2006.
|
|
|
03 December 2007
Prolojik to sponsor Channel 4's Grand Designs
Prolojik will be providing the lighting controls for a forthcoming episode of Channel 4's Grand Designs series. Filming has already commenced on the development by Paul Tarling, which is due for airing in Spring of 2008.
The innovative build has been designed by Paxton Locher Architects and incorporates a number of innovative design features and a state-of-the-art control system.
|
|
|
27 November 2007
Prolojik wins Blink Point lighting controls package
Prolojik has secured the lighting controls package at Blink Point in Southwark, London. Working with Shepard Engineering Services, Prolojik will be supplying a mixture of switched and dimmable lighting controls to this CAT A fitout.
|
|
|
06 November 2007
Evolution House
Prolojik have secured the supply of lighting controls for Edinburgh College of Arts at Evolution House, Edinburgh. Working with Edinburgh College of Art, Prolojik will utilise PL521 1-10V lighting controls and presence detection.
|
|
|
05 November 2007
Prolojik completes fitout of Rio Tinto at Aldermanbury Square
Prolojik has completed the fitout of the executive floor at 5 Aldermanbury Square. This fast moving project was undertaken for Trilectric.
|
|
|
29 October 2007
Prolojik wins refurbishment of Johnson & Johnson PGRD at High Wycombe
Prolojik has secured the fitout of 2 additional blocks as well as the refurbishment of the existing 5 blocks of the Johnson & Johnson High Wycombe facility. Working for Phoenix Electrical under Como, this fast moving project will be completed Q1,08.
|
|
|
10 September 2007
Prolojik secures Fortis fit-out at 5 Aldermanbury Square
Prolojik has won the Fortis Bank fit-out at Aldermanbury Square. Working for Gratte Brothers, the project builds on the builds of the shell & core and Cat A completed by Prolojik earlier in 2007.
|
|
|
29 August 2007
Prolojik completes fit-out for Canopius at 1986 Building
Prolojik has provided a complete turnkey package from design through implementation for the lighting control and terminal HVAC control of three galleries of the 1986 Building at 1 Lime Street.
The fit-out integrates into the existing Prolojik infrastructure within the 1986 Building.
|
|
|
17 July 2007
Prolojik wins Babcock & Brown fit-out at Aldermanbury Square
Prolojik has secured the fit-out for Babcock & Brown at Aldermanbury Square. Working for CEL the project builds on the builds of the shell & core and Cat A completed by Prolojik earlier in 2007.
|
|
|
19 June 2007
Times Report on London's latest “Greenscraper”
The Willis Building, 51 Lime Street
Owner: British Land
Developer: Stanhope and British Land
Size: 29 floors, 520,00 sq ft lettable space
Main tenant: Willis, with 465,000 sq ft
— Beats building regulations requirements for fuel and power conservation by 20 per cent, helped by automatic light sensors and low-energy light bulbs.
— Automatic taps, individual flush sensors, reduced flush, leak detection and rainwater irrigation bring water consumption 30 per cent below average
— Construction waste cut by 30 per cent
|
|
|
13 June 2007
Alistair Darling opens GSK Imperial College Imaging Centre
Trade and Industry Sectary Alistair Darling today opened the GSK Imperial College Imaging Centre at White City. Prolojik has provided the general office lighting and specialist laboratory lighting utilising, DSi, DALI and emergency monitoring.
|
|
|
08 June 2007
Prolojik wins lighting controls package at National Museum of Scotland
Prolojik has won the lighting control package at the National Museum of Scotland. Working for McArthur M&E, Prolojik will be providing lighting controls to the NMS Granton facility.
|
|
|
18 May 2007
Prolojik wins redevelopment of Jones Lang LaSalle at 22-24 Hanover Square
Prolojik has won the lighting control package at 22-24 Hanover Square, London. Working for Gratte Brothers, Prolojik will supply and commission the upgrade of the lighting system.
|
|
|
11 May 2007
Royal Opening Ceremony - Force Communications Centre
The new, state-of-the-art Force Communications Centre at Police Headquarters was opened formally today (May 11, 2007) by His Royal Highness, The Duke of Kent KG.
|
|
|
09 May 2007
Prolojik wins fit-out phase of Willis Tower
Prolojik has secured the fit-out work stream of the Willis Tower. The project will follow in from the shell and core phase and will leverage the infrastructure and equipment used in this phase to provide a seamless integration between the shell and core and fit-out phases.
|
|
|
03 May 2007
The Crown Estate Fitout
Prolojik has secured fit-out phase of The Crown Estates head-quarters at 16 New Burlington Place. Working for Accurro, Prolojik will be reconfiguring the client floors with DALI lighting control and occupancy control. This fit-out reconfiguration follows on from the original new build contract through Skanska in 2005.
|
|
|
07 March 2007
Prolojik completes Huntington Court
Prolojik has completed the refurbishment of the lighting control system at the Huntington CJC. Working with MITIE, Prolojik has supplied occupancy and switching control of the building.
|
|
|
05 March 2007
Prolojik completes new HQ for Prospect
Working for Meica, Prolojik has completed the new headquarters building for the trade union Prospect. The project incorporated an innovative installation including Prolojik's PS330 DALI sensors mounted into Trox chilled beams controlled by PL433 DALI hardwired LCMs in the core areas of each floor.
|
|
|
19 January 2007
Prolojik completes CAT A fit-out of Royex House
Prolojik has completed the shell and core and CAT A fit-out of Royex House, Aldermanbury Square for Gratte Brothers. Prolojik has supplied DALI control of the open plan floors along with switched controls of the core areas.
|